UK Power Networks connections by grid supply point

1,024 connections of 1 MW and over in UK Power Networks's register of 14 Oct 2026, at 54 grid supply points. Contracted volume, not headroom.

Grid supply pointConnectionsAccepted MWConnected MW
Walpole971,9511,312
Bramford1101,3261,013
Norwich751,1261,120
Rayleigh47843.8525.5
Bolney45836.9606.1
Eaton Socon41673.9276.1
Burwell39665.6386
Sundon70661.5476.6
Pelham39631.9234.3
Ninfield33544279.5
Richborough12488.60
Northfleet East38457188.3
Wymondley29398.3235.8
Littlebrook 132kV (SPN)430017.5
Sellindge6264.20
Kemsley28250.6283.7
Tilbury24247.8215.8
Brimsdown (EPN)9239.930
Warley23233.9327.4
Little Horsted3193.20
Canterbury17160293.5
Biggleswade1139.90
Rye House20137.754.2
Chessington41283
Kingsnorth18116.4115
Amersham11102181.5
Richborough/Sellindge 132kV2999.9539.6
Littlebrook 132kV (LPN)590.117.3
West Weybridge1071.916.6
Elstree1867.7157.2
Watford South465.51.8
Braintree1756.7158.8
Barking 132kV (EPN)1250
Beddington 132kV1112105.5
Tottenham71096.7
Willesden 132kV59.8146.9
New Cross 132kV76.637.5
Barking West 33kV (LPN)7551.9
West Ham11326.5
St Johns Wood7218.2
Mill Hill31.62.4
City Road141.534.2
Barking 132kV (LPN)1072
Hackney 132kV101.4
Hackney 66kV208.8
Hurst 132kV304.5
Islington306.8
Laleham2030.2
Lodge Road206.5
New Cross 66kV306.2
Redbridge Supergrid 33kV101
West Thurrock2021.5
Willesden 66kV102
Wimbledon 132kV 3 & 44022