New Cross 66kV grid supply point
3 connections of 1 MW and over at New Cross 66kV in UK Power Networks's register of 14 Oct 2026: 0 MW accepted to connect and 6.2 MW connected. Each row's own figure, added across rows; contracted volume, not headroom.
| Site | Customer | Technology | MW | Status | Target energisation |
|---|---|---|---|---|---|
| Kings College Hospital | Kings College Hospital | Gas | 4.2 | Connected | |
| 301 Camberwell New Road | Walworth Garage | Storage | 1 | Connected | |
| Coniston House {Boiler Room) | London Borough of Southwark | Gas | 1 | Connected |
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.