Willesden 132kV grid supply point
5 connections of 1 MW and over at Willesden 132kV in UK Power Networks's register of 14 Oct 2026: 9.8 MW accepted to connect and 146.9 MW connected. Each row's own figure, added across rows; contracted volume, not headroom.
| Site | Customer | Technology | MW | Status | Target energisation |
|---|---|---|---|---|---|
| Taylor Lane Power Station | Taylor Lane Power Station | Gas | 140 | Connected | |
| Premier Park | Syzygy Consulting | Solar | 6.39 | Accepted to connect | |
| First Way Wembley | UK Power Solutions | Gas | 5 | Connected | |
| Origin Business Park | Segro PLC | Solar | 3.4 | Accepted to connect | |
| Pladis Harlesden Chp | Shenton Group | Gas | 1.86 | Connected |
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.