41 connections of 1 MW and over at Eaton Socon in UK Power Networks's register of 14 Oct 2026: 673.9 MW accepted to connect and 276.1 MW connected. Each row's own figure, added across rows; contracted volume, not headroom.
| Site | Customer | Technology | MW | Status | Target energisation |
|---|---|---|---|---|---|
| (ANM) Caxton Road | IG Renewable Energy UK Limited | Solar | 99.9 | Accepted to connect | |
| Woodwalton Lane | EDF Energy Renewables Limited | Solar | 99.9 | Accepted to connect | |
| Duck End Energy Park | EDP Renewables UK Limited | Solar, Wind | 94.05 | Accepted to connect | |
| (ANM) Land Off Twinwood Road | Pathfinder Clean Energy (PACE) | Solar, Storage | 69 | Accepted to connect | 31 Oct 2028 |
| (ANM) Land North Of Bassmead Manor | Nextpower SPV 16 Limited | Solar | 50 | Accepted to connect | 31 Oct 2028 |
| (ANM) Bushmead Road | Eaton Socon Power Limited | Solar, Storage | 50 | Accepted to connect | 31 Oct 2028 |
| (ANM) Land At Rookery Farm | BF58 Hunts Airfield Solar Limited | Solar, Storage | 49.99 | Accepted to connect | 31 Oct 2032 |
| (ANM - N/A) Cobholden Farm | Cambridge Power Limited | Storage | 49.9 | Accepted to connect | 31 Oct 2032 |
| Little Staughton | AEE Renewables UK 9 Limited | Solar | 40 | Connected | |
| (ANM)Foxholes Farm | Elgin Energy ES CO Limited | Solar | 40 | Accepted to connect | 31 Oct 2028 |
| Waterloo Solar Park, Waterloo Farm | Waterloo Solar Park Limited | Solar | 23 | Connected | |
| Caldecote Manor Farm | Inazin | Solar | 22 | Connected | |
| (ANM - N/A) Lowfield Farm | Lowfield Energy Centre Limited | Solar | 21 | Accepted to connect | 31 Oct 2032 |
| (ANM) Eaton Ford Solar Park | Low Carbon Soilar Park 30 Limted | Solar, Storage | 20 | Accepted to connect | 31 Oct 2032 |
| Upwood Airfield | Abbey Properties Cambridge Limited | Solar | 20 | Connected | |
| (ANM) Vicarage Lane | Thornhill Estates Limited | Solar | 18 | Accepted to connect | 31 Oct 2028 |
| (ANM - N/A) Red House Farm | Anesco Limited | Solar | 16.94 | Connected | |
| Cotton Wind Farm | Npower Renewables | Onshore wind | 16.4 | Connected | |
| Manor Farm | Prosolia | Solar | 15 | Connected | |
| Red Tile Windfarm - 2 | Fenland Windfarms Limited | Onshore wind | 14 | Connected | |
| Croydon Solar Farm | Energy & System Technical Limited | Solar | 14 | Connected | |
| Hoback Farm | Hoback Solar Limited | Solar | 12.95 | Connected | |
| Woolley Hill Wind Farm | RES | Onshore wind | 11.5 | Connected | |
| Wiggin Hill Farm | S.E. Solar (2) Limited | Solar | 10 | Connected | |
| Double Bank Lane | Sun & Alternative Technology Limited | Solar | 9 | Connected | |
| AWS Grafham Water Treatment Works | HBS Group Southern Limited | Solar | 7.04 | Connected | |
| Common Barn Wind Farm Phase 2 | Tci Renewables Limited | Onshore wind | 6.15 | Accepted to connect | 31 Oct 2028 |
| Common Barn West Of A1 Southoe | TCI renewables | Onshore wind | 6.15 | Connected | |
| ((ANM) Stow Road | Anglo Renewables Limited | Solar | 6 | Accepted to connect | 31 Oct 2028 |
| Skylark Meadow | UK Solar Parks Limited | Solar | 5 | Connected | |
| Cantelupe Farm | Harlaxton Engineering Services Limited | Solar | 5 | Connected | |
| Rookery Farm | Prosolia UK Limited | Solar | 5 | Connected | |
| Stubbins Nursery | Stubbins Food Partnerships Limited | Gas | 4.5 | Connected | |
| Huntingdon Wood Recycling Centre 1 - Phs 1 | Energy 10 | Bioenergy | 3.09 | Connected | |
| Godmanchester Landfill Site | Viridis Energy (Norgon) Limited | Bioenergy | 3 | Connected | |
| Warboys Landfill Site | Viridis Energy (Norgen) Limited | Bioenergy | 3 | Connected | |
| Station Farm Landfill Generator | Viridis Energy (Norgon) Limited | Bioenergy | 2.56 | Connected | |
| Ramsey Wind Turbine | REG Ramsey Limited | Onshore wind | 2 | Connected | |
| Puddock Hill | Amber Energy | Gas | 2 | Connected | |
| Lodge Farm Bridge Road | Castle Renewables Limited | Solar | 2 | Connected | |
| Galley Hill Farm | York Green Renewables Limited | Onshore wind | 1 | Connected |
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.