Barking West 33kV (LPN) grid supply point
7 connections of 1 MW and over at Barking West 33kV (LPN) in UK Power Networks's register of 14 Oct 2026: 5 MW accepted to connect and 51.9 MW connected. Each row's own figure, added across rows; contracted volume, not headroom.
| Site | Customer | Technology | MW | Status | Target energisation |
|---|---|---|---|---|---|
| Beckton Sewage Works | Beckton Sewage Works (33kV) | Energy from waste, Bioenergy | 11.4 | Connected | |
| Crossness Sewage Treatment Works | Crossness Sewage Treatment Works | Energy from waste, Fossil - Oil | 11.06 | Connected | |
| Ocado | Ocado | Fossil - Oil | 6.8 | Connected | |
| Gallions Power | AMP Energy Services Limited | Gas | 5 | Connected | |
| Barking Energy Centre | WSP | Gas | 3.8 | Accepted to connect | |
| Warren Energy Centre | Harrods | Gas | 2.6 | Connected | |
| Gascoinge Estate Gen | B&D Energy | Gas | 1.22 | Accepted to connect |
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.