Skylark Meadow

Skylark Meadow, UK Solar Parks Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 5 MW, grid supply point Eaton Socon.

Customer
UK Solar Parks Limited
Status
Connected
Capacity
5 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Eaton Socon
Bulk supply point
Little Barford 33kV
Point of connection
Bourn Primary 11kV
Voltage
11 kV
Date connected
21 Mar 2013
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Caxton Road, Bourn
Postcode
CB23 2SX
Export MPAN
1030083946097

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.