Common Barn Wind Farm Phase 2

Common Barn Wind Farm Phase 2, Tci Renewables Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 6.15 MW, grid supply point Eaton Socon.

Customer
Tci Renewables Limited
Status
Accepted to connect
Capacity
6.15 MW
Technology
Onshore wind (Onshore wind turbines)
Flexible connection
No
Grid supply point
Eaton Socon
Bulk supply point
Little Barford 33kV
Voltage
33 kV
Date accepted
5 Feb 2018
Target energisation
31 Oct 2028
In a connection queue
Yes
Row last updated by the DNO
14 Feb 2023
Licence area
EPN
Address
The Street, St Neots
Postcode
PE19 5XU

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source