Lodge Farm Bridge Road

Lodge Farm Bridge Road, Castle Renewables Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2 MW, grid supply point Eaton Socon.

Customer
Castle Renewables Limited
Status
Connected
Capacity
2 MW
Maximum import capacity
0.02 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Eaton Socon
Point of connection
Huntingdon Grid 11kV
Voltage
11 kV
Date connected
1 Jan 2015
In a connection queue
No
Row last updated by the DNO
14 Dec 2020
Licence area
EPN
Address
Bridge Road, Huntingdon
Postcode
PE28 3AZ
Export MPAN
1050000698380

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.