(ANM) Land Off Twinwood Road

(ANM) Land Off Twinwood Road, Pathfinder Clean Energy (PACE), is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 69 MW, grid supply point Eaton Socon.

Customer
Pathfinder Clean Energy (PACE)
Status
Accepted to connect
Capacity
69 MW
Technology
Solar, Storage (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Eaton Socon
Voltage
132 kV
Date accepted
24 Aug 2020
Target energisation
31 Oct 2028
In a connection queue
Yes
Row last updated by the DNO
14 Dec 2022
Licence area
EPN
Address
Bedford
Postcode
MK41 6AB

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.