Upwood Airfield, Abbey Properties Cambridge Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Eaton Socon.

Customer
Abbey Properties Cambridge Limited
Status
Connected
Capacity
20 MW
Maximum import capacity
0.1 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Eaton Socon
Bulk supply point
Huntingdon Grid 33kV
Voltage
33 kV
Date connected
17 Mar 2014
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Ramsey, Cambs
Postcode
PE28 2LQ
Export MPAN
1050000574685

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.