Warren Energy Centre

Warren Energy Centre, Harrods, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2.6 MW, grid supply point Barking West 33kV (LPN).

Customer
Harrods
Status
Connected
Capacity
2.6 MW
Technology
Gas (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Barking West 33kV (LPN)
Point of connection
Sewell Rd B 11kV
Voltage
11 kV
Date connected
19 Oct 2016
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
London Power Networks plc
Address
Arsenal Way, Royal Arsenal
Postcode
SE18 6TE

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source