Warley 275kV Substation

Warley 275kV Substation (NGET) has 12 projects in NESO's TEC Register of 23 Oct 2026: 1,711 MW in the queue, 57 MW of it Gate 2, 1,129 MW Gate 1, and 205.9 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
12
MW in the queue
1,711 MW
Gate 2 MW
57 MW
Gate 1 MW
1,129 MW
MW connected
205.9 MW
Earliest confirmed date
30 Oct 2028

By technology

TechnologyProjectsMW
Storage121,917
Solar157

Projects at Warley 275kV Substation

ProjectTechnologyMWGateStatusMW effective from
Lebanon Farm 2 BESSStorage275Scoping31 Oct 2030
Warley PV & BESSStorage249.9Scoping31 Oct 2031
Codham Hall BESSStorage249Gate 1Scoping31 Oct 2037
St. Marys Lane - Upminster BESSStorage240Gate 1Scoping31 Oct 2036
Upminster Warley 3Storage240Gate 1Scoping31 Oct 2036
Blanket’s FarmStorage200Gate 1Scoping31 Oct 2038
Warley Battery Energy StorageStorage200Gate 1Scoping31 Oct 2029
WarleyStorage57Gate 2Consents Approved30 Oct 2028
Warley (tertiary)Storage, Solar57Built
Care Brentwood BEGAStorage49.9Built
Clay Tye Farm Phase 1Storage49.5Built
Clay Tye Farm Phase 2Storage49.5Built