Grid GuardianOpen the evidence in the app

Lebanon Farm 2 BESS

Lebanon Farm 2 BESS is a storage project of 275 MW in NESO's TEC Register of 23 Oct 2026, connecting at Warley 275kV Substation (NGET). Status: Scoping.

Customer
CEDARTECH ENERGY LTD
Connection site
Warley 275kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
275 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2030
NESO project number
PRO-003939

Also at Warley 275kV Substation

ProjectTechnologyMW
Blanket’s FarmStorage200
Care Brentwood BEGAStorage49.9
Clay Tye Farm Phase 1Storage49.5
Clay Tye Farm Phase 2Storage49.5
Codham Hall BESSStorage249
St. Marys Lane - Upminster BESSStorage240
Upminster Warley 3Storage240
WarleyStorage57
Warley (tertiary)Storage, Solar57
Warley Battery Energy StorageStorage200
Warley PV & BESSStorage249.9

Source