Grid GuardianOpen the evidence in the app

Blanket’s Farm

Blanket’s Farm is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Warley 275kV Substation (NGET). Status: Scoping. Gate 1.

Customer
Noventum Power Solar 9 Limited
Connection site
Warley 275kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2038
NESO project number
PRO-004469