Codham Hall BESS

Codham Hall BESS is a storage project of 249 MW in NESO's TEC Register of 23 Oct 2026, connecting at Warley 275kV Substation (NGET). Status: Scoping. Gate 1.

Customer
PULSE CLEAN ENERGY LIMITED
Connection site
Warley 275kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
249 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2037
NESO project number
PRO-003972