Grid GuardianOpen the evidence in the app

First Way Wembley

First Way Wembley, UK Power Solutions, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 5 MW, grid supply point Willesden 132kV.

Customer
UK Power Solutions
Status
Connected
Capacity
5 MW
Maximum import capacity
1 MW
Technology
Gas (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Willesden 132kV
Bulk supply point
Leicester Rd Grid 33kV
Point of connection
Bee Primary 11kV
Voltage
11 kV
Date connected
30 Nov 2023
In a connection queue
No
Row last updated by the DNO
14 Oct 2024
Licence area
EPN
Address
Wembley
Postcode
HA9 0TU
Export MPAN
1050001452668

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source