Trent Valley South Connection Node D 400kV Substation

Trent Valley South Connection Node D 400kV Substation (NGET) has 4 projects in NESO's TEC Register of 23 Oct 2026: 6,420 MW in the queue, 5,420 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
4
MW in the queue
6,420 MW
Gate 1 MW
5,420 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Gas14,800
Storage31,620
Solar21,380

Projects at Trent Valley South Connection Node D 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Bute Hydrogen Project 1Gas4,800Gate 1Scoping30 Oct 2035
Stoke BardolphStorage, Solar1,000Scoping31 Oct 2034
Noventum - BudbyStorage, Solar380Gate 1Scoping30 Oct 2035
Stoke BardolphStorage240Gate 1Scoping30 Oct 2034