Stoke Bardolph
Stoke Bardolph is a storage, solar project of 1,000 MW in NESO's TEC Register of 23 Oct 2026, connecting at Trent Valley South Connection Node D 400kV Substation (NGET). Status: Scoping.
- Customer
- Stoke Bardolph 10 Renewables Limited
- Connection site
- Trent Valley South Connection Node D 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 1,000 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 31 Oct 2034
- NESO project number
- PRO-003405
Also at Trent Valley South Connection Node D 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Bute Hydrogen Project 1 | Gas | 4,800 |
| Noventum - Budby | Storage, Solar | 380 |
| Stoke Bardolph | Storage | 240 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.