Stoke Bardolph

Stoke Bardolph is a storage, solar project of 1,000 MW in NESO's TEC Register of 23 Oct 2026, connecting at Trent Valley South Connection Node D 400kV Substation (NGET). Status: Scoping.

Customer
Stoke Bardolph 10 Renewables Limited
Connection site
Trent Valley South Connection Node D 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
1,000 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2034
NESO project number
PRO-003405

Also at Trent Valley South Connection Node D 400kV Substation

ProjectTechnologyMW
Bute Hydrogen Project 1Gas4,800
Noventum - BudbyStorage, Solar380
Stoke BardolphStorage240