Grid GuardianOpen the evidence in the app

Noventum - Budby

Noventum - Budby is a storage, solar project of 380 MW in NESO's TEC Register of 23 Oct 2026, connecting at Trent Valley South Connection Node D 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
NOVENTUM POWER SOLAR 15 LIMITED
Connection site
Trent Valley South Connection Node D 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
380 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2035
NESO project number
PRO-004652

Also at Trent Valley South Connection Node D 400kV Substation

ProjectTechnologyMW
Bute Hydrogen Project 1Gas4,800
Stoke BardolphStorage240
Stoke BardolphStorage, Solar1,000

Source