Sussex and Romney Connection Node B 400kV Substation

Sussex and Romney Connection Node B 400kV Substation (NGET) has 5 projects in NESO's TEC Register of 23 Oct 2026: 1,665 MW in the queue, 1,265 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
5
MW in the queue
1,665 MW
Gate 1 MW
1,265 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage51,665
Solar2740
Demand1500

Projects at Sussex and Romney Connection Node B 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
SAVE OUR PLANETDemand, Storage, Solar500Gate 1Scoping31 Oct 2037
Shipley Road BESSStorage400Consents Approved21 Oct 2031
DRAGON GREEN BESSStorage300Gate 1Scoping31 Oct 2037
Lightsource Shipley PVStorage, Solar240Gate 1Scoping30 Oct 2037
Lanehurst Farm BESSStorage225Gate 1Scoping31 Oct 2037