Lightsource Shipley PV

Lightsource Shipley PV is a storage, solar project of 240 MW in NESO's TEC Register of 23 Oct 2026, connecting at Sussex and Romney Connection Node B 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
Lightsource Renewable UK Development Limited
Connection site
Sussex and Romney Connection Node B 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
240 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2037
NESO project number
PRO-003707

Also at Sussex and Romney Connection Node B 400kV Substation

ProjectTechnologyMW
DRAGON GREEN BESSStorage300
Lanehurst Farm BESSStorage225
SAVE OUR PLANETDemand, Storage, Solar500
Shipley Road BESSStorage400