Lanehurst Farm BESS
Lanehurst Farm BESS is a storage project of 225 MW in NESO's TEC Register of 23 Oct 2026, connecting at Sussex and Romney Connection Node B 132kV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- ELGIN ENERGY ES CO LIMITED
- Connection site
- Sussex and Romney Connection Node B 132kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 225 MW
- Agreement
- Embedded
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2037
- NESO project number
- PRO-005083
Also at Sussex and Romney Connection Node B 132kV Substation
| Project | Technology | MW |
|---|---|---|
| DRAGON GREEN BESS | Storage | 300 |
| Lightsource Shipley PV | Storage, Solar | 240 |
| SAVE OUR PLANET | Demand, Storage, Solar | 500 |
| Shipley Road BESS | Storage | 400 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.