Neilston 400kV Substation

Neilston 400kV Substation (SPT) has 4 projects in NESO's TEC Register of 23 Oct 2026: 1,000 MW in the queue, 600 MW of it Gate 2, 400 MW Gate 1, and 150 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
4
MW in the queue
1,000 MW
Gate 2 MW
600 MW
Gate 1 MW
400 MW
MW connected
150 MW
Earliest confirmed date
31 Oct 2029

By technology

TechnologyProjectsMW
Storage31,150
Reactive Compensation10

Projects at Neilston 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Neilston 400kV Greener Grid ParkStorage600Gate 2Consents Approved31 Oct 2029
Hurlet BatteryStorage400Gate 1Scoping31 Oct 2033
Neilston 132Storage150Built31 Oct 2025
Neilston Synchronous CompensationReactive Compensation0Consents Approved12 Jun 2025