Neilston 132

Neilston 132 is a storage project of 150 MW in NESO's TEC Register of 23 Oct 2026, connecting at Neilston 132kV Substation (SPT). Status: Built.

Customer
NEILSTON ENERGY LIMITED
Connection site
Neilston 132kV Substation
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
150 MW
Agreement
Direct Connection
Status
Built
MW effective from
31 Oct 2025
NESO project number
PRO-001343

Also at Neilston 132kV Substation

ProjectTechnologyMW
Hurlet BatteryStorage400
Neilston 400kV Greener Grid ParkStorage600
Neilston Synchronous CompensationReactive Compensation0