Neilston 132
Neilston 132 is a storage project of 150 MW in NESO's TEC Register of 23 Oct 2026, connecting at Neilston 132kV Substation (SPT). Status: Built.
- Customer
- NEILSTON ENERGY LIMITED
- Connection site
- Neilston 132kV Substation
- Transmission owner
- SPT
- Technology
- Storage
- Capacity (TEC)
- 150 MW
- Agreement
- Direct Connection
- Status
- Built
- MW effective from
- 31 Oct 2025
- NESO project number
- PRO-001343
Also at Neilston 132kV Substation
| Project | Technology | MW |
|---|---|---|
| Hurlet Battery | Storage | 400 |
| Neilston 400kV Greener Grid Park | Storage | 600 |
| Neilston Synchronous Compensation | Reactive Compensation | 0 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.