Grid GuardianOpen the evidence in the app

Neilston 400kV Greener Grid Park

Neilston 400kV Greener Grid Park is a storage project of 600 MW in NESO's TEC Register of 23 Oct 2026, connecting at Neilston 400kV Substation (SPT). Status: Consents Approved. Gate 2.

Customer
Statkraft UK Ltd
Connection site
Neilston 400kV Substation
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
600 MW
Agreement
Direct Connection
Gate
Gate 2
Status
Consents Approved
MW effective from
31 Oct 2029
NESO project number
PRO-001419

Also at Neilston 400kV Substation

ProjectTechnologyMW
Hurlet BatteryStorage400
Neilston 132Storage150
Neilston Synchronous CompensationReactive Compensation0

Source