East Claydon 400kV Substation

East Claydon 400kV Substation (NGET) has 6 projects in NESO's TEC Register of 23 Oct 2026: 5,150 MW in the queue, 2,600 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
6
MW in the queue
5,150 MW
Gate 1 MW
2,600 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage65,150
Solar44,000
Demand12,050
Nuclear11,000
Onshore wind11,000
Reactive Compensation11,000

Projects at East Claydon 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
East Claydon Green Energy CentreDemand, Storage, Solar1,025–2,050Awaiting Consents1 Oct 2034, 31 Oct 2038
East Claydon High Impact Green Energy Hub (HIGEH) 1Storage, Nuclear, Solar, Reactive Compensation, Onshore wind1,000Gate 1Scoping6 Dec 2036
East Claydon Greener Grid ParkStorage650Gate 1Scoping30 Nov 2034
East Claydon StorageStorage500Gate 1Scoping1 Oct 2026
RosefieldStorage, Solar500Awaiting Consents31 Oct 2031
Alderton PV & BESS StationStorage, Solar450Gate 1Scoping31 Oct 2037