Grid GuardianOpen the evidence in the app

Alderton PV & BESS Station

Alderton PV & BESS Station is a storage, solar project of 450 MW in NESO's TEC Register of 23 Oct 2026, connecting at East Claydon 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
BNRG ALBION LIMITED
Connection site
East Claydon 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
450 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2037
NESO project number
PRO-002764

Also at East Claydon 400kV Substation

ProjectTechnologyMW
East Claydon Green Energy CentreDemand, Storage, Solar1,025–2,050
East Claydon Greener Grid ParkStorage650
East Claydon High Impact Green Energy Hub (HIGEH) 1Storage, Nuclear, Solar, Reactive Compensation, Onshore wind1,000
East Claydon StorageStorage500
RosefieldStorage, Solar500

Source