East Claydon High Impact Green Energy Hub (HIGEH) 1

East Claydon High Impact Green Energy Hub (HIGEH) 1 is a storage, nuclear, solar, reactive compensation, onshore wind project of 1,000 MW in NESO's TEC Register of 23 Oct 2026, connecting at East Claydon 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
EAST CLAYDON STORAGE LIMITED
Connection site
East Claydon 400kV Substation
Transmission owner
NGET
Technology
Storage, Nuclear, Solar, Reactive Compensation, Onshore wind
Capacity (TEC)
1,000 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
6 Dec 2036
NESO project number
PRO-002652