Grid GuardianOpen the evidence in the app

Navenby GEC (Ethos Green)

Navenby GEC (Ethos Green) is a storage, solar project of 580 MW in NESO's TEC Register of 23 Oct 2026, connecting at Navenby 400kV Substation (NGET). Status: Awaiting Consents. Gate 1.

Customer
NAVENBY GREEN ENERGY CENTRE LTD
Connection site
Navenby 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
580 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Awaiting Consents
MW effective from
30 Oct 2033
NESO project number
PRO-003936

Also at Navenby 400kV Substation

ProjectTechnologyMW
Bicker DroveStorage400
Bicker Fen BESSStorage, Solar249.9
Cliff Hill Energy FarmStorage, Solar800
Denton Estate Solar PV and BESSStorage, Solar129
EwerbyDemand, Storage, Solar500
Forepower Lincoln (250) LtdStorage240
Housham PV & BESSStorage, Solar240
SpringwellStorage, Solar400–1,600
Vicarage Drove BESS LimitedStorage160

Source