Ewerby

Ewerby is a demand, storage, solar project of 500 MW in NESO's TEC Register of 23 Oct 2026, connecting at Navenby 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
Leoda Solar Farm Limited
Connection site
Navenby 400kV Substation
Transmission owner
NGET
Technology
Demand, Storage, Solar
Capacity (TEC)
500 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2035
NESO project number
PRO-002017

Also at Navenby 400kV Substation

ProjectTechnologyMW
Bicker DroveStorage400
Bicker Fen BESSStorage, Solar249.9
Cliff Hill Energy FarmStorage, Solar800
Denton Estate Solar PV and BESSStorage, Solar129
Forepower Lincoln (250) LtdStorage240
Housham PV & BESSStorage, Solar240
Navenby GEC (Ethos Green)Storage, Solar580
SpringwellStorage, Solar400–1,600
Vicarage Drove BESS LimitedStorage160