Grid GuardianOpen the evidence in the app

Forepower Lincoln (250) Ltd

Forepower Lincoln (250) Ltd is a storage project of 240 MW in NESO's TEC Register of 23 Oct 2026, connecting at Navenby 132kV Substation (NGET). Status: Scoping. Gate 1.

Customer
FOREPOWER LINCOLN (250) LIMITED
Connection site
Navenby 132kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
240 MW
Agreement
Embedded
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2034
NESO project number
PRO-004455

Also at Navenby 132kV Substation

ProjectTechnologyMW
Bicker DroveStorage400
Bicker Fen BESSStorage, Solar249.9
Cliff Hill Energy FarmStorage, Solar800
Denton Estate Solar PV and BESSStorage, Solar129
EwerbyDemand, Storage, Solar500
Housham PV & BESSStorage, Solar240
Navenby GEC (Ethos Green)Storage, Solar580
SpringwellStorage, Solar400–1,600
Vicarage Drove BESS LimitedStorage160

Source