Grid GuardianOpen the evidence in the app

Hookers Farm BESS

Hookers Farm BESS is a storage project of 250 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bolney 132kV Substation (NGET). Status: Consents Approved.

Customer
Ancleggan Limited
Connection site
Bolney 132kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
250 MW
Agreement
Embedded
Status
Consents Approved
MW effective from
31 Oct 2031
NESO project number
PRO-002308