Grid GuardianOpen the evidence in the app

Bolney (tertiary)

Bolney (tertiary) is a storage, solar project of 57 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bolney 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
BOLNEY GREEN LIMITED
Connection site
Bolney 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
57 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
29 May 2028
NESO project number
PRO-000380

Also at Bolney 400kV Substation

ProjectTechnologyMW
BolneyStorage, Solar47.5
Bolney FarmStorage, Solar200
Bolney Grid Stability ServicesReactive Compensation0
CONTEGO Battery Storage ProjectStorage35.8
Hookers Farm BESSStorage250
KingsfoldStorage, Solar49.9
Rampion Extension Offshore Wind FarmOffshore wind1,200
ShorehamGas460