Grid GuardianOpen the evidence in the app

Burghfield

Burghfield is a thermal project of 47 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bramley 400kV Substation (NGET). Status: Built.

Customer
SSE GENERATION LIMITED
Connection site
Bramley 400kV Substation
Transmission owner
NGET
Technology
Thermal
Capacity (TEC)
47 MW
Agreement
Embedded
Status
Built
NESO project number
PRO-000870

Also at Bramley 400kV Substation

ProjectTechnologyMW
Bramley (tertiary)Storage, Solar57
Bramley BESSStorage50–57
Conrad (Basingstoke) LimitedStorage20
Pamber FarmStorage480

Source