Bramley (tertiary)
Bramley (tertiary) is a storage, solar project of 57 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bramley 400kV Substation (NGET). Status: Under Construction/Commissioning. Gate 2.
- Customer
- BRAMLEY SOLAR LIMITED
- Connection site
- Bramley 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 57 MW
- Agreement
- Direct Connection
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- MW effective from
- 30 Oct 2027
- NESO project number
- PRO-000396
Also at Bramley 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Bramley BESS | Storage | 50–57 |
| Burghfield | Thermal | 47 |
| Conrad (Basingstoke) Limited | Storage | 20 |
| Pamber Farm | Storage | 480 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.