Bramley BESS
Bramley BESS is a storage project of 50–57 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bramley 400kV Substation (NGET). Status: Under Construction/Commissioning. Gate 2.
- Customer
- BRAMLEY BESS LIMITED
- Connection site
- Bramley 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 50–57 MW
- Agreement
- Direct Connection
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- MW effective from
- 30 Oct 2027, 31 Oct 2037
- NESO project number
- PRO-001104-1, PRO-001104-2
Also at Bramley 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Bramley (tertiary) | Storage, Solar | 57 |
| Burghfield | Thermal | 47 |
| Conrad (Basingstoke) Limited | Storage | 20 |
| Pamber Farm | Storage | 480 |
Source