Grid GuardianOpen the evidence in the app

Axminster - New Connection

Axminster - New Connection is a storage project of 120 MW in NESO's TEC Register of 23 Oct 2026, connecting at Axminster 132kV Substation (NGET). Status: Scoping. Gate 1.

Customer
ENSO GREEN HOLDINGS B LIMITED
Connection site
Axminster 132kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
120 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Jun 2029
NESO project number
PRO-001356

Also at Axminster 132kV Substation

ProjectTechnologyMW
AxminsterStorage120
AxminsterStorage49.9
Axminster BESSStorage150
Old Park FarmStorage, Solar200

Source