Axminster

Axminster is a storage project of 49.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at Axminster 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
PIVOTED POWER LLP
Connection site
Axminster 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
49.9 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2027
NESO project number
PRO-001143

Also at Axminster 400kV Substation

ProjectTechnologyMW
AxminsterStorage120
Axminster - New ConnectionStorage120
Axminster BESSStorage150
Old Park FarmStorage, Solar200