Axminster BESS

Axminster BESS is a storage project of 150 MW in NESO's TEC Register of 23 Oct 2026, connecting at Axminster 132kV Substation (NGET). Status: Scoping. Gate 1.

Customer
CSE25 LIMITED
Connection site
Axminster 132kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
150 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2028
NESO project number
PRO-001740

Also at Axminster 132kV Substation

ProjectTechnologyMW
AxminsterStorage120
AxminsterStorage49.9
Axminster - New ConnectionStorage120
Old Park FarmStorage, Solar200