Grid GuardianOpen the evidence in the app

Wickham Hall

Wickham Hall, Wickham Hall Solar Battery Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 10 MW, grid supply point Pelham.

Customer
Wickham Hall Solar Battery Limited
Status
Accepted to connect
Capacity
10 MW
Technology
Solar, Storage (Photovoltaic)
Flexible connection
No
Grid supply point
Pelham
Bulk supply point
Bishops Stortford Grid 33kV
Voltage
33 kV
Date accepted
9 Oct 2015, 17 Mar 2017
Target energisation
12 Jan 2024, 6 Jun 2025
In a connection queue
Yes
Row last updated by the DNO
14 Nov 2024
Licence area
EPN
Address
Hadham Road, Bishops Stortford
Postcode
CM23 1JG

Register rows

RowStatusMWTarget
1Accepted to connect1012 Jan 2024
2Accepted to connect106 Jun 2025

Rows at one site are not summed.

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source