Whittlesey Wind Turbine, Whittlesey Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2 MW, grid supply point Walpole.

Customer
Whittlesey Limited
Status
Connected
Capacity
2 MW
Technology
Onshore wind (Onshore wind turbines)
Flexible connection
No
Grid supply point
Walpole
Bulk supply point
Peterborough Central 33kV
Point of connection
Funthams Ln Primary 11kV
Voltage
11 kV
Date connected
20 Aug 2008
In a connection queue
No
Row last updated by the DNO
15 Jan 2021
Licence area
EPN
Address
Funthams Lane, Walpole
Postcode
PE7 2PB
Export MPAN
1030056991471

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.