Westcott Venture Park, Phase 2A and Phase 2B

Westcott Venture Park, Phase 2A and Phase 2B, Shanks Waste Management Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1.1 MW, grid supply point Sundon.

Customer
Shanks Waste Management Limited
Status
Connected
Capacity
1.1 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Sundon
Bulk supply point
Aylesbury East Grid 33kV
Point of connection
Waddesdon Primary 11kV
Voltage
11 kV
Date connected
9 Mar 2012
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Westcott Venture Park, Aylesbury
Postcode
HP18 0NX
Export MPAN
1030082301361

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.