West Thaxted Solar Farm

West Thaxted Solar Farm, Cutlers Solar Farm Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Pelham.

Customer
Cutlers Solar Farm Limited
Status
Accepted to connect
Capacity
20 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Pelham
Bulk supply point
Thaxted Grid 33kV
Voltage
33 kV
Date accepted
20 Dec 2019
Target energisation
12 Jan 2024
In a connection queue
Yes
Row last updated by the DNO
16 Jan 2023
Licence area
EPN
Address
Watling Lane, Thaxted
Postcode
CM6 2QY

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.