Wallace Power

Wallace Power, AMP Energy Services, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4 MW, grid supply point Wymondley.

Customer
AMP Energy Services
Status
Connected
Capacity
4 MW
Technology
Fossil - Oil (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Wymondley
Bulk supply point
Wymondley Grid 33kV
Point of connection
North Hitchin Primary 11kV
Voltage
11 kV
Date connected
18 Dec 2020
In a connection queue
No
Row last updated by the DNO
14 Dec 2021
Licence area
EPN
Address
Wallace Power, Hitchin
Postcode
SG4 0SL
Export MPAN
1050001945459

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.