Vine Solar Farm

Vine Solar Farm, Emotion Energy Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 45 MW, grid supply point Wymondley.

Customer
Emotion Energy Limited
Status
Connected
Capacity
45 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Wymondley
Voltage
33 kV
Date connected
5 Mar 2016
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Wendy, Royston
Postcode
SG8 0HJ
Export MPAN
1050000996150

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.