Grid GuardianOpen the evidence in the app

Twineham Grange Manor,Coombes Solar

Twineham Grange Manor,Coombes Solar, Bolney Green Energy Hub 1 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49 MW, grid supply point Bolney.

Customer
Bolney Green Energy Hub 1 Limited
Status
Accepted to connect
Capacity
49 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
No
Grid supply point
Bolney
Voltage
132 kV
Date accepted
10 May 2017
Target energisation
31 Oct 2026
In a connection queue
Yes
Row last updated by the DNO
14 Jun 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Haywards Heath
Postcode
RH17 5NH

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source