Turncole Wind Farm

Turncole Wind Farm, RES UK & Ireland Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 18.4 MW, grid supply point Rayleigh.

Customer
RES UK & Ireland Limited
Status
Connected
Capacity
18.4 MW
Technology
Onshore wind (Onshore wind turbines)
Flexible connection
No
Grid supply point
Rayleigh
Bulk supply point
Fleethall Grid 33kV
Voltage
33 kV
Date connected
1 Dec 2016
In a connection queue
No
Row last updated by the DNO
14 Nov 2023
Licence area
EPN
Address
Southminster
Postcode
CM0 8NE
Export MPAN
1050001078651

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.