Grid GuardianOpen the evidence in the app

Tring Road

Tring Road, Terra Firma Energy Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.99 MW, grid supply point Sundon.

Customer
Terra Firma Energy Limited
Status
Accepted to connect
Capacity
49.99 MW
Technology
Gas (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Sundon
Voltage
132 kV
Date accepted
13 Jul 2018
Target energisation
31 Oct 2024
In a connection queue
Yes
Row last updated by the DNO
12 Jul 2024
Licence area
EPN
Address
Tring Road, Tring
Postcode
HP23 4RA

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.