Grid GuardianOpen the evidence in the app

Thurstons Farm

Thurstons Farm, QE Development HoldCo, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 60 MW, grid supply point Pelham.

Customer
QE Development HoldCo
Status
Accepted to connect
Capacity
60 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Pelham
Bulk supply point
Thaxted Grid
Voltage
132 kV
Date accepted
18 Jan 2026
In a connection queue
Yes
Row last updated by the DNO
13 Feb 2026
Licence area
EPN
Address
Robinhood End, Braintree
Postcode
CM7 4JB

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source