Three Bridges
Three Bridges, Pathfinder Clean Energy (PACE) UK Dev Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 15 MW, grid supply point Norwich.
- Customer
- Pathfinder Clean Energy (PACE) UK Dev Limited
- Status
- Accepted to connect
- Capacity
- 15 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- No
- Grid supply point
- Norwich
- Bulk supply point
- Sall Grid 132/33kV
- Point of connection
- East Dereham Primary 33kV
- Voltage
- 33 kV
- Date accepted
- 21 Feb 2020
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Jul 2025
- Licence area
- EPN
- Address
- South Of Elsing Road, Dereham
- Postcode
- NR20 3EW
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.